济南水泥稳定碎石:混合料生产、摊铺及碾压的标准

来源:http://www.ycgjglcl.com/ 日期:2025-09-08

  混合料生产、摊铺及碾压

  Production, paving, and rolling of mixed materials

  水泥稳定土类材料的配合比设计步骤,应按本规范第7.2.2条的有关规定进行,且应符合下列规定:

  The mix design steps for cement stabilized soil materials shall be carried out in accordance with the relevant provisions of Article 7.2.2 of this specification, and shall comply with the following provisions:

  1 试配时水泥掺量宜按表7.5.3选取。

  The cement dosage should be selected according to Table 7.5.3 during trial mixing.

  水泥稳定土类材料试配水泥掺量

  Cement stabilized soil material trial mix cement dosage

  注:①当强度要求较高时,水泥用量可增加1%。

  Note: When the strength requirement is high, the cement dosage can be increased by 1%.

  2 当采用厂拌法生产时,水泥掺量应比试验剂量加0.5%,水泥最小掺量粗粒土、中粒土应为3%,细粒土为4%。

  When using the factory mixing method for production, the cement dosage should be 0.5% higher than the test dosage. The minimum cement dosage for coarse-grained soil and medium grained soil should be 3%, and for fine-grained soil it should be 4%.

  3 水泥稳定土料材料7d抗压强度:对城市快速路、主干路基层为3~4MPa,对底基层为1.5~2.5MPa;对其他等级道路基层为2.5~3MPa,底基层为1.5~2.0MPa。

  The 7-day compressive strength of cement stabilized soil material is 3-4MPa for urban expressways and main road base, and 1.5-2.5MPa for subbase; For other levels of road base, the pressure is 2.5-3MPa, and for sub base, it is 1.5-2.0MPa.

  城镇道路中使用水泥稳定土类材料,宜集中拌制。

  Cement stabilized soil materials are used in urban roads and should be mixed centrally.

  集中搅拌水泥稳定土类材料应符合下列规定:

  Centralized mixing of cement stabilized soil materials shall comply with the following regulations:

  1 集料应过筛,级配符合设计要求。

  The aggregate should be sieved and graded according to the design requirements.

  2 混合料配合比符合要求,计量准确、含水量符合施工要求、搅拌均匀。

  The mixing ratio of the mixture meets the requirements, the measurement is accurate, the moisture content meets the construction requirements, and the mixing is uniform.

  3 搅拌厂应向现场提供产品合格证及水泥用量、粒料级配、混合料配合比、R7强度标准值。

  The mixing plant should provide product qualification certificates, cement dosage, aggregate gradation, mix proportion, and R7 strength standard values to the site.

  4 水泥稳定土类材料运输时,应采取措施防止水分损失。

  When transporting cement stabilized soil materials, measures should be taken to prevent moisture loss.

  摊铺应符合下列规定:base64_image

  Paving shall comply with the following regulations:

  1、 施工前应通过试验确定压实系数。水泥土的压实系数宜为1.53~1.58;水泥稳定砂砾的压实系数宜为1.30~1.35。

  1. The compaction coefficient should be determined through testing before construction. The compaction coefficient of cement soil should be between 1.53 and 1.58; The compaction coefficient of cement stabilized gravel should be 1.30-1.35.

  2、 宜采用专用摊铺机械摊铺,采用两台摊铺机并排摊铺时,两台摊铺机的型号及磨损程度宜相同。在施工期间,两台摊铺机 的前后间距宜不大于10m,且两个施工段面纵向应有300~400mm的重叠。。

  2. It is advisable to use specialized paving machinery for paving. When two paving machines are used for parallel paving, the models and wear levels of the two paving machines should be the same. During construction, the distance between two pavers should not exceed 10m, and there should be a longitudinal overlap of 300-400mm between the two construction sections..

  3、 水泥稳定土类材料自搅拌至摊铺完成,不得超过3h。应按当班施工长度计算用料量。

  3. The self mixing of cement stabilized soil materials to the completion of paving shall not exceed 3 hours. The amount of materials used shall be calculated based on the construction length of the shift.

  4、 分层摊铺时,应在下层养护7d后,方可摊铺上层材料。

  4. When laying in layers, the upper layer material can only be laid after the lower layer has been cured for 7 days.

  5、底基层、基层分层施工时,根据工程需要可采用两层连续摊铺、分层碾压一次成型工艺。

  5. When constructing the sub base layer and base layer in layers, a two-layer continuous paving and layer by layer rolling process can be adopted according to the needs of the project.

  6、摊铺前应做好路侧培槽土与中分带侧模的施工,在摊铺过程中宜设立纵向模板。

  6. Before paving, the construction of roadside trench soil and median strip side formwork should be done well, and longitudinal formwork should be set up during the paving process.

  7、施工前做好支模工作。支模时底面要平齐、一体;模板与模板之间用高强度钢筋串联。支撑钢 模板的支架、木方应连接牢固,钢钎深扎地表以下至少30cm。

  7. Do a good job of formwork support before construction. When supporting the mold, the bottom surface should be flat and integrated; High strength steel bars are connected in series between templates. The brackets and wooden beams supporting the steel formwork should be firmly connected, and the steel drill should be deeply penetrated at least 30cm below the ground surface.

  8、采用两层连续摊铺时,下层质量出现问题时,上层应同时处理。

  8. When using two layers of continuous paving, if there are quality problems with the lower layer, the upper layer should be dealt with simultaneously.

  9、 对无法使用机械摊铺的超宽路段,应采用人工同步摊铺、修整,并同时碾压成型。

  9. For ultra wide road sections that cannot be paved by machinery, manual synchronous paving, trimming, and simultaneous compaction should be used.

  10、摊铺机前宜增设橡胶挡板,橡胶挡板底部距下承层距离宜不大于100mm。中线离析严重时,摊 铺机应安装反向叶片。

  10. A rubber baffle should be added in front of the paver, and the distance between the bottom of the rubber baffle and the lower bearing layer should not exceed 100mm. When the centerline segregation is severe, the paver should be equipped with reverse blades.

  11、在摊铺机后面应设专人消除粗细集料离析现象,及时铲除局部粗集料堆积或离析的部位,并用 新拌混合料填补。

  11. A dedicated person should be assigned behind the paver to eliminate the phenomenon of coarse and fine aggregate segregation, promptly remove the local accumulation or segregation of coarse aggregate, and fill it with fresh mixed material.

  7.5.7 碾压应符合下列规定:

  7.5.7 Rolling compaction shall comply with the following regulations:

  1 应在含水量等于或略大于最佳含水量时进行。碾压找平应符合本规范第7.2.8条的有关规定。

  It should be carried out when the moisture content is equal to or slightly higher than the optimal moisture content. Rolling and leveling shall comply with the relevant provisions of Article 7.2.8 of this specification.

  2 压实时,遵循初压→复压→终压的程序,达到压实遍数为止。 6.6.4 采用钢轮压路机初压时,宜采用双钢轮压路机稳压2~3遍,再用激振力大于35t的重型振动压路机、18~21t三轮压路机或25t以上的轮胎压路机继续碾压密实,最后采用双钢轮压路机碾压,消除 轮迹。采用胶轮压路机初压时,应采用25t以上的重胶轮压路机稳压1~2遍,错轮不超过1/3的轮迹 带宽度,再采用重型振动压路机碾压密实,最后采用双钢轮压路机碾压,消除轮迹。。

  When compacting, follow the procedure of initial compaction → re compaction → final compaction until the number of compaction passes is reached. 6.6.4 When using a steel wheel roller for initial compaction, it is advisable to use a double steel wheel roller to stabilize the pressure for 2-3 times, and then use a heavy-duty vibrating roller with an excitation force greater than 35t, an 18-21t three wheel roller, or a tire roller with an excitation force of 25t or more to continue compacting. Finally, a double steel wheel roller should be used for compaction to eliminate wheel marks. When using a rubber tired roller for initial compaction, a heavy rubber tired roller with a capacity of 25 tons or more should be used to stabilize the pressure for 1-2 times. The staggered wheel should not exceed 1/3 of the width of the wheel track, and then a heavy vibratory roller should be used for compaction. Finally, a double drum roller should be used for compaction to eliminate wheel tracks..

  3 水泥稳定土类材料,宜在水泥初凝时间到达前碾压成活。

  Cement stabilized soil materials should be compacted and compacted before the initial setting time of cement is reached.

  4 当使用振动压路机时,应符合环境保护和周围建筑物及地下管线、构筑物的安全要求。

  When using a vibratory roller, it should comply with environmental protection and safety requirements for surrounding buildings, underground pipelines, and structures.

  5、 碾压过程中,压路机严禁随意停放,应停放在已碾压完成的路段。

  5. During the compaction process, the roller is strictly prohibited from being parked randomly and should be parked on the already compacted road section.

  6、碾压完成后,尽快进行压实度检测,并及时把检测结果反馈给现场施工人员,以便及时对压实 度不足的部位进行补压。

  6. After the compaction is completed, the compaction degree should be tested as soon as possible, and the test results should be promptly fed back to the on-site construction personnel, so as to promptly supplement the areas with insufficient compaction degree.

  本文由  济南水稳碎石  友情奉献.更多有关的知识请点击  http://www.ycgjglcl.com/   真诚的态度.为您提供为全面的服务.更多有关的知识我们将会陆续向大家奉献.敬请期待.

  This article is contributed by Jinan Water Stable Gravel Friendship For more related knowledge, please click http://www.ycgjglcl.com/ Sincere attitude To provide you with comprehensive services We will gradually contribute more relevant knowledge to everyone Coming soon.